TBM reaches
Choti Chaupar -Stops due to Sargasuli
IIT Delhi
will give certificate
The metro
work in progress between Badi Chaupar and Chandpole has been stopped in view of
security measures of Sargasuli. The first tunnel-boring machine (TBM) reached
Choti Chaupar from Chandpole during the digging process. Omicron Company of
Greece had already generated a certificate of safety to Sargasuli from the
digging work. IIT Delhi is investigating this certificate.
Second TBM
team will reach in 45 days-
The first
and the second TBM machines have put 940 and 390 rings respectively. The second
TBM machine has reached shop no 380 while digging from Chandpole. This machine
will take 45 days to reach Choti Chaupar. The first TBM machine will reach Badi
Chaupar in June. According to Metro’s CMD N.C Goyal, “ A letter for
investigation request has been sent to IIT Delhi. The report is expected to
arrive in 4 days.”