Jaipur Metro

Jaipur Metro
Jaipur Metro

Tuesday, 27 December 2016

Jaipur Metro Toilet locator app

Jaipur Metro Toilet locator app

Under Swachh Bharat abhiyan "Jaipur Metro" launched Toilet locator app which will help to find nearest public toilet. Initially 18 toilets of 9 metro station information published on this app. 

Jaipur Metro Toilet locator app
Jaipur Metro Toilet locator app

Friday, 23 December 2016

Chandpole to Badi Chaupar underground Metro work progress

Chandpole to Badi Chaupar underground Metro work progress 

Jaipur metro rail corporation has been taking land from Devsthan department, Jaipur Nagar Nigam and Police department and working at a fast phase to cover The phase 1 b between Chandpole and Badi Chaupar. This underground area covers a distance of 1836 meter and is supposed to finish by june 2018.

But the finishing wok is taking a lot of time and the date of starting of metro phase 1 b on track may differ. However both tunnels have been completed. But the roof work of stations have not been completed. The top and middle roof of Choti chaupar has been completed and the third roof has to be put up. The labor work of all three roofs at Badi Chaupar is still remaining.

Sas Tax will not be included in the electricity bill.

Jaipur Metro has been giving Sas Tax to the electricity department till now, this would not be continued further. This decision was taken in high power committee meeting with chief secretary. The committee had put forward that when this tax is not levied on Indian railways then it should be warded off in Jaipur Metro too. Till now Metro was giving 80 to 85 paise per unit sas tax.

Ramganj area pathway would be open between 5 to 7 Jan. The pathway area between Badi chaupar and ramganj is closed due to construction work and it can be opened between 5 to 7 jan. Tripolia area pathway was opeend on the occasion of Diwali. The first tunnel has 35 meter digging left to be completed



Chandpole to Badi Chaupar underground Metro work progress
Chandpole to Badi Chaupar underground Metro work progress 

Tuesday, 20 December 2016